About Us - NAL Passive Safety News - NAL Demonstration Day Customer Login & Register Media Gallery Technical Downloads
 

Case Study - TEMPORARY FOUNDATIONS

RS Temporary Foundations | Buckingham Palace

The NAL Temporary Foundation systems were recently utilised by TFL during the renewal and upgrading of the traffic signals outside Buckingham Palace.

The existing signals were removed for four months and during these works the Temporary Foundations allowed the site to operate as normal with full pedestrian facilities. This solution was used due to their stable footprint, ability to conceal all cables from the public and the ease of moving them away from site for the London Marathon, Parades and State Visits. 

Project : Temporary Traffic Signals, The Mall and Buckingham Palace
Product : Temporary Foundations with RS115
Client : TfL